Expansion projects unfolding at River Rd. and Student Recreation Complex

Categories: Expansion Updates,Featured,Membership category,News

UREC-Expansion-Update

Fields at River Rd.


Out at the fields at River Rd the new North drive way and parking lot have been paved and curbs within the new parking area will be poured today. The chained fencing surrounding the softball fields has begun. The exterior fence around the entire site continues this week. The west boundary of the fencing has been completed around near River Rd. From here, they will begin to work east in order to complete this portion of the project.

 

Student Recreation Complex


As for the parking and tennis at the Student Recreation Complex, the site work has begun to form out a set of tennis courts. They have continued to dig out the drainage and the area nearest to Lod Cook is now being filled in. Facility Services have successfully installed the data line for the new parking meter to be installed along the north side of the Clubhouse.

 

Recent Photos